New Post | Settings | Change Layout | Edit HTML | Moderate Comments | Sign Out O level A level A A1 A2 home private tuition physics chemistry mathematics maths biology trigonometry physics H2 H1 Science Score tutor tuition tuition tutoring tuition biology economics assessment exam exams exampapers exam papers NIE JC Secondary School Singapore Education tutor teach teacher school student agency

O lvl E Maths: Ratio Rate Proportion

RI 1998 Sec 3 EOY Q2

3 men, working 8 hours a day, can finish a job in 6 days. How many days would it take 2 men working 9 hours a day to complete the same job, assuming that they work at the same rate?

*************************

Answer:

Total number of man-hours when 3 men are working 8 hours a day for 6 days
= (3 * 8 * 6) man-hours

Days taken to complete when 2 men are working 9 hours a day
= (3 * 8 * 6) / (2 * 9)
= 8 days